Barrio EnergyGrid
Barrio Grid / Texas counties / Hale County

Hale County, Texas: power grid and siting data

SPS (non-ERCOT) owns most of the substations near the county center. It has 25 mapped substations, owned mostly by SPS (non-ERCOT), Lighthouse Elec Co Op Inc and Golden Spread Electric Co Op Inc; the highest voltage is 345 kV. The ERCOT queue lists 3 generation projects (2 gas and 1 solar) and 2 battery storage projects here.

25substations
345 kVhighest voltage
3generation projects queued
2battery projects queued
n/aload zone, 7-day avg $/MWh
Map of substations in Hale County, Texas

Substations in Hale County

1 at 345 kV, 1 at 230 kV, 1 at 138 kV, 5 at 115 kV, 17 at 69 kV and below.

SubstationVoltageOwnerLines
Tuco345 kVSPS (non-ERCOT)11map
Unnamed station230 kVGolden Spread Electric Co Op Inc2map
Unnamed station138 kVLighthouse Elec Co Op Inc4map
Hale Co115 kVSPS (non-ERCOT)6map
Unnamed station115 kVHorne Mark3map
Unnamed station115 kVGaskins Nathan & Benita3map
Tap305460115 kVnot recorded3map
Unnamed station115 kVTaters Inc2map
Unnamed station69 kVSPS (non-ERCOT)5map
Tap30242269 kVHoward Trust Partnership3map
Unnamed station69 kVMusil Joseph William3map
Unnamed station69 kVSPS (non-ERCOT)2map
Unnamed station69 kVSammann Kurt & Jess W2map
Unnamed station69 kVSPS (non-ERCOT)2map
Unnamed station69 kVSPS (non-ERCOT)1map
Unnamed station69 kVEhj11 Property Llc1map
Unnamed station69 kVGolden Spread Electric Co Op Inc1map
Unnamed station69 kVLighthouse Elec Co Op Inc1map
Unnamed station69 kVLighthouse Elec Co Op Inc1map
Unnamed station69 kVSPS (non-ERCOT)1map
Unnamed station69 kVOccidental Permian Ltd1map
Unnamed station69 kVSwisher Electric Co Op Inc1map
Unnamed station69 kVLighthouse Elec Co Op Inc1map
Unnamed station69 kVSouth Plains Elect Co Op1map
Unnamed station69 kVLighthouse Elec Co Op Inc1map

ERCOT interconnection queue

3 generation projects are queued in Hale County: 2 gas and 1 solar. By stage: 1 with a signed interconnection agreement and 2 in full interconnection study. 2 battery storage projects are queued, 0 with a signed interconnection agreement.

From the ERCOT GIS report. Project names, developers, MW and dates are on Pro.

Planned transmission

No planned substations, lines or upgrades are recorded in Hale County.

Wholesale power prices

No price data.

ERCOT day-ahead settlement point prices. Hourly history, battery spreads and real-time prices are on the map.

Data centers and large loads

2 announced data center campuses in Hale County, 2 at or above ERCOT's 75 MW large load threshold.

Jurisdiction

Nearest city to the county center: Hale Center (0.5 mi). Outside city limits and ETJ, development falls under county rules and state law. City limits and estimated ETJ are on the map.

Nearby counties

See Hale County on the map

Every substation, line, queue project, pipeline and price node in Texas, plus Dub, an AI landman who answers questions about any spot. Free account, no card.