Swisher Electric Coop owns most of the substations near the county center. It has 11 mapped substations, owned mostly by SPS (non-ERCOT), Gibson John Mark and Griffith Family Trust; the highest voltage is 115 kV. The ERCOT queue lists 4 generation projects (3 solar and 1 wind) and 3 battery storage projects here.
Substations in Swisher County
5 at 115 kV, 6 at 69 kV and below.
| Substation | Voltage | Owner | Lines | |
|---|---|---|---|---|
| Unnamed station | 115 kV | SPS (non-ERCOT) | 5 | map |
| Kress | 115 kV | SPS (non-ERCOT) | 5 | map |
| Tap305416 | 115 kV | Gibson John Mark | 3 | map |
| Swisher | 115 kV | SPS (non-ERCOT) | 3 | map |
| Unnamed station | 115 kV | Griffith Family Trust | 1 | map |
| Tap305262 | 69 kV | Wilhelm Wayne | 3 | map |
| Unnamed station | 69 kV | Nustar Logistics Lp | 3 | map |
| Unnamed station | 69 kV | Swisher Electric Coop | 1 | map |
| Unnamed station | 69 kV | Frost Ralph E | 1 | map |
| Happy City | 69 kV | SPS (non-ERCOT) | 1 | map |
| Unnamed station | 69 kV | Perry Tyline Trust | 1 | map |
ERCOT interconnection queue
4 generation projects are queued in Swisher County: 3 solar and 1 wind. By stage: 1 with a signed interconnection agreement and 3 in full interconnection study. 3 battery storage projects are queued, 1 with a signed interconnection agreement.
From the ERCOT GIS report. Project names, developers, MW and dates are on Pro.
Planned transmission
No planned substations, lines or upgrades are recorded in Swisher County.
Wholesale power prices
No price data.
ERCOT day-ahead settlement point prices. Hourly history, battery spreads and real-time prices are on the map.
Jurisdiction
Nearest city to the county center: Tulia (0.9 mi). Outside city limits and ETJ, development falls under county rules and state law. City limits and estimated ETJ are on the map.
Nearby counties
See Swisher County on the map
Every substation, line, queue project, pipeline and price node in Texas, plus Dub, an AI landman who answers questions about any spot. Free account, no card.
Sources: HIFLD and OpenStreetMap substations and lines, ERCOT GIS report (queue, 2026-09), ERCOT day-ahead prices, TxDOT and StratMap boundaries, Barrio Energy research. Updated 2026-11-09. Screening data only; the serving utility confirms capacity.