Deaf Smith Electric Coop owns most of the substations near the county center. It has 10 mapped substations, owned mostly by Deaf Smith Electric Coop, SPS (non-ERCOT) and Oncor; the highest voltage is 345 kV. The ERCOT queue lists 5 generation projects (4 solar and 1 wind) and 2 battery storage projects here.

10substations
345 kVhighest voltage
5generation projects queued
2battery projects queued
n/aload zone, 7-day avg $/MWh
Map of substations in Castro County, Texas

Substations in Castro County

2 at 345 kV, 1 at 138 kV, 6 at 115 kV, 1 at 69 kV and below.

SubstationVoltageOwnerLines
Ogallala345 kVOncor5map
Unnamed station345 kVDimmitt Corn Mill Llc2map
Unnamed station138 kVDeaf Smith Electric Coop1map
Castro County115 kVSPS (non-ERCOT)5map
Tap302494115 kVBailey Co Electric Coop3map
Tap308103115 kVSides George H3map
Unnamed station115 kVnot recorded3map
Unnamed station115 kVDeaf Smith Electric Coop1map
Unnamed station115 kVSPS (non-ERCOT)0map
Unnamed station69 kVDeaf Smith Electric Coop1map

ERCOT interconnection queue

5 generation projects are queued in Castro County: 4 solar and 1 wind. By stage: 2 with a signed interconnection agreement and 3 in full interconnection study. 2 battery storage projects are queued, 1 with a signed interconnection agreement.

From the ERCOT GIS report. Project names, developers, MW and dates are on Pro.

Planned transmission

No planned substations, lines or upgrades are recorded in Castro County.

Wholesale power prices

No price data.

ERCOT day-ahead settlement point prices. Hourly history, battery spreads and real-time prices are on the map.

Jurisdiction

Nearest city to the county center: Dimmitt (2.2 mi). Outside city limits and ETJ, development falls under county rules and state law. City limits and estimated ETJ are on the map.

Nearby counties

See Castro County on the map

Every substation, line, queue project, pipeline and price node in Texas, plus Dub, an AI landman who answers questions about any spot. Free account, no card.

Sources: HIFLD and OpenStreetMap substations and lines, ERCOT GIS report (queue, 2026-09), ERCOT day-ahead prices, TxDOT and StratMap boundaries, Barrio Energy research. Updated 2026-11-09. Screening data only; the serving utility confirms capacity.