Barrio EnergyGrid
Barrio Grid / Texas counties / Jasper County

Jasper County, Texas: power grid and siting data

Jasper Newton Elec Coop owns most of the substations near the county center. It has 14 mapped substations, owned mostly by Jasper Newton Elec Coop, Jnec and Entergy (non-ERCOT); the highest voltage is 138 kV. The ERCOT queue lists 0 generation projects and 0 battery storage projects here.

14substations
138 kVhighest voltage
0generation projects queued
0battery projects queued
n/aload zone, 7-day avg $/MWh
Map of substations in Jasper County, Texas

Substations in Jasper County

12 at 138 kV, 2 at 69 kV and below.

SubstationVoltageOwnerLines
Sam Dam138 kVEntergy (non-ERCOT)7map
Jasper138 kVEntergy (non-ERCOT)6map
Evadale138 kVEntergy (non-ERCOT)4map
Unnamed station138 kVJnec4map
Mill Creek138 kVJnec4map
Unnamed station138 kVJasper Newton Elec Coop3map
Unnamed station138 kVJasper Newton Elec Coop2map
Unnamed station138 kVJasper Newton Elec Coop2map
Unnamed station138 kVJasper Newton Elec Coop2map
Kirbyville138 kVJnec2map
Unnamed station138 kVJasper Newton Elec Coop2map
Unnamed station138 kVJnec1map
Horton Hill69 kVDeep East Tx Electric Coop Inc3map
Kirbyville69 kVnot recorded1map

ERCOT interconnection queue

No generation projects are queued in Jasper County. No battery storage projects are queued.

From the ERCOT GIS report. Project names, developers, MW and dates are on Pro.

Planned transmission

No planned substations, lines or upgrades are recorded in Jasper County.

Wholesale power prices

No price data.

ERCOT day-ahead settlement point prices. Hourly history, battery spreads and real-time prices are on the map.

Jurisdiction

Nearest city to the county center: Kirbyville (8.4 mi). Outside city limits and ETJ, development falls under county rules and state law. City limits and estimated ETJ are on the map.

Nearby counties

See Jasper County on the map

Every substation, line, queue project, pipeline and price node in Texas, plus Dub, an AI landman who answers questions about any spot. Free account, no card.

Sources: HIFLD and OpenStreetMap substations and lines, ERCOT GIS report (queue, 2026-09), ERCOT day-ahead prices, TxDOT and StratMap boundaries, Barrio Energy research. Updated 2026-11-09. Screening data only; the serving utility confirms capacity.