Cass County, Texas: power grid and siting data
Bowie Cass Electric Coop owns most of the substations near the county center. It has 18 mapped substations, owned mostly by Graphic Packaging International Llc, Tyner Karen & Stanley Glaze and Bowie Cass Electric Coop; the highest voltage is 345 kV. The ERCOT queue lists 0 generation projects and 0 battery storage projects here.
Substations in Cass County
2 at 345 kV, 7 at 138 kV, 9 at 69 kV and below.
| Substation | Voltage | Owner | Lines | |
|---|---|---|---|---|
| Tap308045 | 345 kV | not recorded | 3 | map |
| Unnamed station | 345 kV | not recorded | 1 | map |
| Tap302587 | 138 kV | not recorded | 3 | map |
| Unnamed station | 138 kV | not recorded | 2 | map |
| Unnamed station | 138 kV | Graphic Packaging International Llc | 2 | map |
| Unnamed station | 138 kV | Graphic Packaging International Llc | 2 | map |
| Unnamed station | 138 kV | Tyner Karen & Stanley Glaze | 2 | map |
| Unnamed station | 138 kV | Bowie Cass Electric Coop | 2 | map |
| Unnamed station | 138 kV | not recorded | 1 | map |
| Unnamed station | 69 kV | Bryan John A Sr | 4 | map |
| Unnamed station | 69 kV | SWEPCO (AEP, non-ERCOT) | 3 | map |
| Tap305166 | 69 kV | Tyner Karen & Stanley Glaze | 3 | map |
| Tap310798 | 69 kV | not recorded | 3 | map |
| Unnamed station | 69 kV | Bowie Cass Electric Coop | 2 | map |
| Unnamed station | 69 kV | SWEPCO (AEP, non-ERCOT) | 2 | map |
| Unnamed station | 69 kV | not recorded | 2 | map |
| Unnamed station | 69 kV | Darenco Inc | 1 | map |
| Unnamed station | 69 kV | not recorded | 1 | map |
ERCOT interconnection queue
No generation projects are queued in Cass County. No battery storage projects are queued.
From the ERCOT GIS report. Project names, developers, MW and dates are on Pro.
Planned transmission
No planned substations, lines or upgrades are recorded in Cass County.
Wholesale power prices
No price data.
ERCOT day-ahead settlement point prices. Hourly history, battery spreads and real-time prices are on the map.
Data centers and large loads
- Entitled, Not Energized: 55 MW in Salisbury, 73 MW Out of Bankruptcy in Bryan, and TVA's $1.5 Million-a-Megawatt Toll Edge Cases 2026-10-13
- $161 a Kilowatt-Month in Tulsa, 333 Watts a Foot in Dowagiac: The Middle Market Prices Live Power Edge Cases 2026-09-08
- Power First, Tenant Later Edge Cases 2026-06-16
Jurisdiction
Nearest city to the county center: Linden (3.6 mi). Outside city limits and ETJ, development falls under county rules and state law. City limits and estimated ETJ are on the map.
Nearby counties
See Cass County on the map
Every substation, line, queue project, pipeline and price node in Texas, plus Dub, an AI landman who answers questions about any spot. Free account, no card.
Sources: HIFLD and OpenStreetMap substations and lines, ERCOT GIS report (queue, 2026-09), ERCOT day-ahead prices, TxDOT and StratMap boundaries, Barrio Energy research. Updated 2026-11-09. Screening data only; the serving utility confirms capacity.