Scurry County, Texas: power grid and siting data
Scurry County is in ERCOT's WEST load zone. It has 32 mapped substations, owned mostly by Oncor, AEP Texas and Golden Spread Electric Cooperative; the highest voltage is 345 kV. The ERCOT queue lists 9 generation projects (7 solar and 2 wind) and 8 battery storage projects here.
Substations in Scurry County
10 at 345 kV, 18 at 138 kV, 1 at 115 kV, 3 at 69 kV and below. The 30 highest-voltage stations are listed; the map shows all 32.
| Substation | Voltage | Owner | Lines | |
|---|---|---|---|---|
| Tonkawa | 345 kV | Oncor | 10 | map |
| Scurry | 345 kV | Oncor | 8 | map |
| Dermott | 345 kV | Oncor | 6 | map |
| Bluff Creek | 345 kV | Oncor | 5 | map |
| Pyron Wind Farm | 345 kV | E On | 1 | map |
| Colorado Basin | 345 kV | Oncor | 1 | map |
| Plainview | 345 kV | Golden Spread Electric Cooperative | 0 | map |
| Scurry Sante Fe | 345 kV | Oncor | 0 | map |
| Nzrt_exds_s1 | 345 kV | AEP Texas | map | |
| Andromeda Solar Gen | 345 kV | AEP Texas | map | |
| Golden Switching Station | 138 kV | Oncor | 3 | map |
| Sacroc | 138 kV | Oncor | 3 | map |
| Unnamed station | 138 kV | Kinder Morgan | 3 | map |
| Sun Switching Station | 138 kV | Oncor | 3 | map |
| Tap310910 | 138 kV | Exxon | 3 | map |
| Ennis Creek Switching Station | 138 kV | Oncor | 2 | map |
| Exxon Sharon Ridge | 138 kV | Exxon | 2 | map |
| Fluvanna | 138 kV | Golden Spread Electric Cooperative | 2 | map |
| Exxon Sharon Ridge | 138 kV | Exxon | 1 | map |
| Brazos Wind 1 | 138 kV | Shell | 1 | map |
| Union | 138 kV | Golden Spread Electric Cooperative | 1 | map |
| Camp Springs Wind 1 | 138 kV | Invenergy | 1 | map |
| Unnamed station | 138 kV | Et S Permian Pipeline Co Llc | 1 | map |
| Snyder | 138 kV | Oncor | 1 | map |
| Unnamed station | 138 kV | Kinder Morgan | 0 | map |
| Oxy Cogdell | 138 kV | Occidental Petroleum | 0 | map |
| Unnamed station | 138 kV | Lamb Caleb | 0 | map |
| Scurry Switching Station | 138 kV | Brazos | 0 | map |
| Unnamed station | 115 kV | Circle M Welding Services Inc | 0 | map |
| Lake Thomas | 69 kV | Oncor | 1 | map |
ERCOT interconnection queue
9 generation projects are queued in Scurry County: 7 solar and 2 wind. By stage: 3 with a signed interconnection agreement, 3 in full interconnection study and 3 done with the full study. 8 battery storage projects are queued, 1 with a signed interconnection agreement.
From the ERCOT GIS report. Project names, developers, MW and dates are on Pro.
Planned transmission
3 planned grid projects touch Scurry County: 3 new or rebuilt lines, 2 at 345 kV or above.
Wholesale power prices
The WEST load zone averaged $57.31/MWh day-ahead over the last 7 days. Nearest generator pricing nodes: SNY_BESS_RN $62.10, ENDPARK_ESS1 $18.96 and CROSSTRL_RN $66.35.
ERCOT day-ahead settlement point prices. Hourly history, battery spreads and real-time prices are on the map.
Data centers and large loads
2 announced data center campuses in Scurry County, 1 at or above ERCOT's 75 MW large load threshold.
- SB Energy is hosting a community open house on the proposed Scurry County data center Fox 34 KJTV 2026-09-29
- Energy Vault breaks ground on SnyderAI campus for Crusoe Spark Business Wire 2026-07-27
- 32 Plants, 287 Million Tons: Somebody Finally Added Up the Texas Gas Buildout The Grid Report 2026-07-03
- Energy Vault breaks ground on Snyder AI for Crusoe Spark POWER Magazine
Jurisdiction
Nearest city to the county center: Snyder (0 mi). Outside city limits and ETJ, development falls under county rules and state law. City limits and estimated ETJ are on the map.
Nearby counties
See Scurry County on the map
Every substation, line, queue project, pipeline and price node in Texas, plus Dub, an AI landman who answers questions about any spot. Free account, no card.
Sources: HIFLD and OpenStreetMap substations and lines, ERCOT GIS report (queue, 2026-09), ERCOT day-ahead prices, TxDOT and StratMap boundaries, Barrio Energy research. Updated 2026-11-09. Screening data only; the serving utility confirms capacity.