Kenedy County, Texas: power grid and siting data

Kenedy County is in ERCOT's SOUTH load zone. It has 9 mapped substations, owned mostly by AEP Texas, Pattern Energy and Iberdrola; the highest voltage is 345 kV. The ERCOT queue lists 3 generation projects (2 solar and 1 wind) and 1 battery storage project here.

9substations
345 kVhighest voltage
3generation projects queued
1battery projects queued
$48.57SOUTH zone, 7-day avg $/MWh
Map of substations in Kenedy County, Texas

Substations in Kenedy County

5 at 345 kV, 4 at 138 kV.

SubstationVoltageOwnerLines
Ajo Switching Station345 kVAEP Texas3map
Baffin Collector Station345 kVAEP Texasmap
Sarita345 kVAEP Texasmap
Stella345 kVAEP Texasmap
Stella Poi345 kVAEP Texasmap
Gulf Wind138 kVPattern Energy4map
Penascal138 kVIberdrola1map
F. Yturria138 kVSTEC1map
Armstrong138 kVAEP Texas0map

ERCOT interconnection queue

3 generation projects are queued in Kenedy County: 2 solar and 1 wind. By stage: 2 in full interconnection study and 1 done with the full study. 1 battery storage project is queued, 0 with a signed interconnection agreement.

From the ERCOT GIS report. Project names, developers, MW and dates are on Pro.

Planned transmission

2 planned grid projects touch Kenedy County: 1 new or rebuilt line and 1 substation upgrade, 2 at 345 kV or above.

Wholesale power prices

The SOUTH load zone averaged $48.57/MWh day-ahead over the last 7 days. Nearest generator pricing nodes: STELLA_RN $44.67, BBREEZE_1_2 $44.45 and ELSAUZ_ALL $44.45.

ERCOT day-ahead settlement point prices. Hourly history, battery spreads and real-time prices are on the map.

Jurisdiction

Nearest city to the county center: San Perlita (28.6 mi). Outside city limits and ETJ, development falls under county rules and state law. City limits and estimated ETJ are on the map.

Nearby counties

See Kenedy County on the map

Every substation, line, queue project, pipeline and price node in Texas, plus Dub, an AI landman who answers questions about any spot. Free account, no card.

Sources: HIFLD and OpenStreetMap substations and lines, ERCOT GIS report (queue, 2026-09), ERCOT day-ahead prices, TxDOT and StratMap boundaries, Barrio Energy research. Updated 2026-11-09. Screening data only; the serving utility confirms capacity.