El Paso County, Texas: power grid and siting data

El Paso Electric Company owns most of the substations near the county center. It has 62 mapped substations, owned mostly by El Paso Electric Co, El Paso Electric Company and City Of El Paso; the highest voltage is 345 kV. The ERCOT queue lists 0 generation projects and 0 battery storage projects here.

62substations
345 kVhighest voltage
0generation projects queued
0battery projects queued
n/aload zone, 7-day avg $/MWh
Map of substations in El Paso County, Texas

Substations in El Paso County

3 at 345 kV, 38 at 115 kV, 21 at 69 kV and below. The 30 highest-voltage stations are listed; the map shows all 62.

SubstationVoltageOwnerLines
Newman345 kVCity Of El Paso13map
Caliente345 kVEl Paso Electric Co7map
Picante345 kVnot recorded6map
Ascarte115 kVEl Paso Electric Co7map
Lane115 kVEl Paso Electric Company6map
Austin115 kVEl Paso Electric Co5map
Dyer115 kVEl Paso Electric Co4map
Montoya115 kVEl Paso Electric Co4map
Scottsdale115 kVEl Paso Electric Co4map
Vista115 kVEl Paso Electric Co4map
Austin North115 kVEl Paso Electric Co4map
Sunset North115 kVEl Paso Electric3map
Coyote115 kVEl Paso Electric Co3map
Leo115 kVEl Paso Electric Co3map
Biggs115 kVnot recorded3map
Gr115 kVBbc Army Integrated Llc3map
Montwood115 kVEl Paso Electric Company3map
Sparks115 kVEl Paso Electric Company3map
Cromo115 kVnot recorded3map
Duranzo115 kVThe El Paso Electric Company2map
Shearman115 kVEl Paso Electric2map
Fort Bliss115 kVnot recorded2map
Thorn115 kVEl Paso Electric Co2map
Copper115 kVEl Paso Electric Co2map
Pelicano115 kVEl Paso Electric Company2map
Diamond Head115 kVEl Paso Electric Company2map
Pendale115 kVEl Paso Electric Company2map
Milagro115 kVCity Of El Paso2map
Marlow115 kVWestern Refining Co Lp2map
Wrangler115 kVEl Paso Electric Company2map

ERCOT interconnection queue

No generation projects are queued in El Paso County. No battery storage projects are queued.

From the ERCOT GIS report. Project names, developers, MW and dates are on Pro.

Planned transmission

No planned substations, lines or upgrades are recorded in El Paso County.

Wholesale power prices

No price data.

ERCOT day-ahead settlement point prices. Hourly history, battery spreads and real-time prices are on the map.

Data centers and large loads

3 announced data center campuses in El Paso County, 2 at or above ERCOT's 75 MW large load threshold.

Jurisdiction

Nearest city to the county center: El Paso (0 mi). Outside city limits and ETJ, development falls under county rules and state law. City limits and estimated ETJ are on the map.

Nearby counties

See El Paso County on the map

Every substation, line, queue project, pipeline and price node in Texas, plus Dub, an AI landman who answers questions about any spot. Free account, no card.

Sources: HIFLD and OpenStreetMap substations and lines, ERCOT GIS report (queue, 2026-09), ERCOT day-ahead prices, TxDOT and StratMap boundaries, Barrio Energy research. Updated 2026-11-09. Screening data only; the serving utility confirms capacity.